Buyela kuBhulogi

Progress Payment Certificates in SA Construction: A Complete Guide

Wakha Team 16 imizuzu kufundza
Progress Payment Certificates in SA Construction: A Complete Guide

Progress payment certificates are the lifeblood of construction cash flow. In South Africa, where delayed payments cost contractors billions annually, understanding how payment certificates work under different contract forms — JBCC, NEC, and GCC — is essential for maintaining healthy cash flow and avoiding disputes.

Unlike traditional businesses that invoice upon delivery, construction contractors must fund materials, labour, and overhead costs upfront, then wait for payment based on work completed. This creates a cash flow gap that can cripple even well-run construction companies. Payment certificates bridge this gap by providing structured, regular payments based on progress.

This comprehensive guide explains what progress payment certificates are, how they work under different South African contract forms, what’s included in calculations, common errors and disputes, and how digital tools can automate the entire process.

What Is a Progress Payment Certificate?

A progress payment certificate is a formal document issued by the principal agent (architect, engineer, or quantity surveyor) that certifies the value of work completed by the contractor and authorises payment by the employer. The certificate serves as both a valuation document and a payment instruction.

Key characteristics:

  • Valuation document — States the value of work completed to date
  • Payment instruction — Authorises payment of the certified amount
  • Legally binding — Creates an obligation on the employer to pay
  • Regular intervals — Issued monthly or at contract-specified intervals
  • Net amount — Shows the amount due after deductions

Payment certificates are the mechanism through which contractors receive regular payments throughout the project, rather than waiting until completion. They’re issued under standard contract forms used in South Africa: JBCC (Joint Building Contracts Committee), NEC (New Engineering Contract), and GCC (General Conditions of Contract).

Types of Payment Certificates Across Different Contracts

South African construction uses three main contract forms, each with slightly different payment certificate processes:

JBCC Interim Payment Certificates

Under JBCC PBA 2018 (Principal Building Agreement), interim payment certificates are issued monthly throughout the construction period.

Process:

  1. Contractor submits payment claim by specified date (typically 25th of month)
  2. Principal agent assesses work completed
  3. Principal agent issues certificate within 7-14 days
  4. Employer pays within 14 days of certificate date

Certificate includes:

  • Gross value of work completed
  • Value of variations
  • Total gross value
  • Retention deduction (typically 5-10%)
  • Previous payments deducted
  • Net amount due

Retention release:

  • 50% released at practical completion (penultimate certificate)
  • Remaining 50% released at final completion (final certificate)

NEC Payment Assessments

Under NEC4 (New Engineering Contract), the project manager assesses payment monthly and issues payment certificates.

Process:

  1. Contractor submits payment application
  2. Project manager assesses payment due
  3. Project manager issues payment certificate
  4. Employer pays within 3 weeks of assessment date

Certificate includes:

  • Price for work done to date
  • Amounts due for compensation events (variations)
  • Amounts to be paid or corrected
  • Retention (if applicable)
  • Previous payments
  • Net amount due

Key differences from JBCC:

  • More flexible assessment process
  • Compensation events (variations) handled differently
  • Different retention mechanisms
  • Shorter payment period (3 weeks vs 14 days)

GCC Payment Certificates

Under GCC 2015 (General Conditions of Contract), the principal agent issues payment certificates monthly.

Process:

  1. Contractor submits payment claim
  2. Principal agent assesses work completed
  3. Principal agent issues certificate
  4. Employer pays within contract-specified period (typically 14-30 days)

Certificate includes:

  • Value of work completed
  • Value of variations
  • Retention deduction
  • Previous payments
  • Net amount due

Retention release:

  • Typically released at practical completion and final completion
  • Specific terms vary by contract

The Payment Certificate Lifecycle

Understanding the complete lifecycle helps you manage the process effectively and avoid delays.

Stage 1: Contractor Payment Claim

The process begins when the contractor submits a payment claim (also called a payment application or valuation).

Claim contents:

  • Statement of work completed during the period
  • Measurement sheets or supporting documentation
  • Details of variations claimed
  • Materials on site (if applicable)
  • Any other amounts claimed (preliminaries, adjustments, etc.)

Timing:

  • Must be submitted by contract deadline (typically 25th of month for JBCC)
  • Late claims may be excluded from current certificate
  • Include all work completed up to claim date

Best practices:

  • Submit claims on time, every time
  • Include detailed supporting documentation
  • Clearly identify variations and additional work
  • Use consistent measurement methods
  • Keep copies of all claims submitted

Stage 2: Assessment by Principal Agent

The principal agent (or project manager under NEC) assesses the contractor’s claim.

Assessment process:

  • Site inspection to verify work completed
  • Measurement of quantities completed
  • Valuation using contract rates
  • Assessment of work quality
  • Valuation of variations
  • Calculation of retention
  • Deduction of previous payments

Assessment criteria:

  • Work must be completed to contract standards
  • Quantities measured accurately
  • Rates applied from contract or agreed rates
  • Variations properly authorised
  • Retention calculated correctly
  • Previous payments accounted for

Timing:

  • Must be completed within contract deadline (typically 7-14 days)
  • Late assessments delay payments
  • Thorough assessment prevents disputes

Stage 3: Certificate Issuance

The principal agent issues the payment certificate.

Certificate contents:

  • Certificate number and date
  • Project name and contract number
  • Period covered
  • Gross value of work completed
  • Value of variations
  • Total gross value
  • Retention deducted
  • Previous payments deducted
  • Net amount due
  • Payment due date

Certificate format:

  • Professional, clear presentation
  • All calculations shown
  • Supporting schedules attached (if required)
  • Signed by principal agent
  • Copies distributed to all parties

Timing:

  • Must be issued within contract deadline
  • Late certificates breach contract terms
  • Creates payment obligation on employer

Stage 4: Payment by Employer

The employer pays the certified amount.

Payment requirements:

  • Paid by due date specified in certificate
  • Paid in full (unless valid set-off)
  • Paid to contractor’s nominated account
  • Payment confirmation provided

Timing:

  • JBCC: 14 days from certificate date
  • NEC: 3 weeks from assessment date
  • GCC: Contract-specified period (typically 14-30 days)

Late payment consequences:

  • Breach of contract
  • Interest on overdue amounts (if contract provides)
  • Potential suspension of work by contractor
  • Damage to relationship

What’s Included in Payment Certificates

Understanding what’s included helps you prepare accurate claims and understand certificate calculations.

Work Done

The primary component is work actually completed during the period.

Included:

  • Work completed to contract standards
  • Measured quantities at contract rates
  • Preliminaries (site establishment, overheads) proportionally
  • Work completed but not yet measured (at provisional value)

Excluded:

  • Work not yet started
  • Defective work (until rectified)
  • Work not meeting contract standards
  • Work outside contract scope (unless authorised variation)

Valuation methods:

  • Bill of quantities rates — Use rates from original bill
  • Schedule of rates — Use rates from schedule
  • Proportional valuation — For preliminaries and overheads
  • Provisional sums — For work covered by provisional sums

Materials on Site

Some contracts allow payment for materials delivered to site but not yet incorporated into work.

JBCC:

  • Materials on site may be included if contract provides
  • Typically limited to specific materials (e.g., structural steel, precast concrete)
  • Must be properly stored and protected
  • Value limited to contract rates

NEC:

  • Materials on site handled differently
  • May be included in payment assessment
  • Subject to contract terms

GCC:

  • Materials on site typically not included
  • Payment only for work completed

Best practices:

  • Check contract terms for materials on site provisions
  • Document materials delivered with photos and records
  • Store materials properly to maintain quality
  • Claim materials on site only if contract allows

Variations

Variations are changes to the original contract scope, price, or conditions.

Included in certificates:

  • Authorised variation orders executed during the period
  • Variations valued using contract methods
  • Provisional variations (if contract allows)

Excluded:

  • Variations authorised but not yet executed
  • Unauthorised work (not variations)
  • Variations not yet valued

Valuation methods:

  • Bill rates — Using rates from original bill of quantities
  • Fair rates — Negotiated rates for work not covered by bill rates
  • Cost plus — Actual cost plus overhead and profit percentage

Retentions

Retention is a percentage of the gross payment amount held back as security.

Retention rates:

  • Typically 5-10% of gross value
  • Varies by contract and project type
  • Applied to gross value including variations

Retention accumulation:

  • Retention accumulates throughout project
  • Total retention = sum of all retention deductions
  • Released in stages (typically 50% at practical completion, 50% at final completion)

Retention purpose:

  • Security for defects during defects liability period
  • Security for incomplete work
  • Protection for employer

Previous Payments

All previous payments must be deducted from the current certificate.

Included:

  • All previous interim payment certificates
  • Advance payments (if any)
  • Direct payments made by employer
  • Any other payments under the contract

Payment tracking:

  • Maintain accurate records of all payments
  • Ensure no double-counting
  • Account for payment adjustments or corrections
  • Verify payment records match bank statements

Adjustments and Corrections

Various adjustments may be included or deducted.

Common adjustments:

  • Fluctuations (if contract provides)
  • Advance payment recoveries
  • Defect deductions (if contract allows)
  • Set-offs (if contract allows)
  • Interest on late payments (if applicable)

Adjustment documentation:

  • All adjustments must be properly documented
  • Contract terms must allow adjustments
  • Adjustments should be explained in certificate

Common Errors and Disputes

Payment certificate errors and disputes are costly and time-consuming. Understanding common issues helps prevent them.

Error 1: Late Payment Claims

Problem: Contractor submits payment claim after contract deadline.

Impact:

  • Claim may be excluded from current certificate
  • Payment delayed to next certificate period
  • Cash flow impact
  • Potential breach of contract

Prevention:

  • Set reminders for claim deadlines
  • Prepare claims in advance
  • Submit claims early, not on deadline day
  • Use automated systems to track deadlines

Error 2: Incomplete Documentation

Problem: Payment claim lacks supporting documentation.

Impact:

  • Principal agent can’t assess claim properly
  • Under-valuation of work
  • Delayed certificate issuance
  • Disputes over amounts

Prevention:

  • Include detailed measurement sheets
  • Provide photos of work completed
  • Document variations properly
  • Maintain clear records

Error 3: Incorrect Retention Calculations

Problem: Retention calculated incorrectly.

Impact:

  • Over-retention reduces cash flow
  • Under-retention exposes employer
  • Disputes over retention amounts
  • Final account complications

Prevention:

  • Understand contract retention terms
  • Calculate retention correctly on gross value
  • Track retention accumulation accurately
  • Verify retention calculations

Error 4: Variation Valuation Disputes

Problem: Disagreement over variation rates or scope.

Impact:

  • Delayed variation payments
  • Cash flow impact
  • Disputes and potential adjudication
  • Project delays

Prevention:

  • Obtain variation orders before work
  • Agree rates before executing work
  • Document variation work thoroughly
  • Include variations in claims promptly

Error 5: Late Certificate Issuance

Problem: Principal agent issues certificate after contract deadline.

Impact:

  • Delayed payments
  • Breach of contract
  • Potential interest claims
  • Strained relationships

Prevention:

  • Principal agent planning and resource allocation
  • Early contractor claim submission
  • Automated reminders and workflows
  • Clear contract deadlines

Error 6: Under-Valuation of Work

Problem: Principal agent values work below contractor’s assessment.

Impact:

  • Reduced cash flow
  • Disputes over measurement
  • Potential adjudication
  • Project delays

Prevention:

  • Clear measurement standards
  • Regular site meetings
  • Detailed supporting documentation
  • Fair and transparent process

Digital vs Manual Payment Certificates

The choice between digital and manual payment certificate processes significantly impacts efficiency, accuracy, and cash flow.

Manual Payment Certificates

Process:

  • Contractor prepares claim manually (spreadsheet or paper)
  • Principal agent assesses manually
  • Certificate typed or handwritten
  • Calculations done manually
  • Distribution via email or post

Challenges:

  • Time-consuming — Hours spent on calculations and preparation
  • Error-prone — Manual calculations lead to mistakes
  • Slow — Process takes days or weeks
  • Inconsistent — Different formats and methods
  • No integration — Separate from project management
  • Difficult tracking — Hard to track payment status

Costs:

  • Administrative time
  • Error correction time
  • Delayed payments
  • Dispute resolution costs

Digital Payment Certificates

Process:

  • Contractor submits claim digitally
  • System calculates amounts automatically
  • Certificate generated automatically
  • Digital distribution and tracking
  • Integration with project management

Benefits:

  • Time savings — Automatic calculations eliminate manual work
  • Accuracy — Automatic calculations reduce errors
  • Speed — Certificates generated in minutes
  • Consistency — Standardised format and calculations
  • Integration — Links with work completion, site diary, variations
  • Tracking — Real-time payment status visibility

Costs:

  • Software subscription (typically R2,000-R7,000/month)
  • Training time (minimal with good software)
  • Implementation (usually quick)

Return on investment:

  • Time savings: 10-20 hours per month per project
  • Faster payments: Reduced payment delays
  • Error reduction: Fewer disputes and corrections
  • Better cash flow: Faster certificate generation = faster payments

How Wakha Generates Payment Certificates

Wakha Construction & Property Development Management Software automates the entire payment certificate process, from contractor claims to certificate generation and payment tracking.

Auto-Calculation

Wakha automatically calculates payment certificate amounts:

  • Work completed — Values work based on progress tracking
  • Variations — Includes authorised variations at agreed rates
  • Retention — Calculates retention automatically based on contract terms
  • Previous payments — Tracks and deducts all previous payments
  • Net amount — Calculates final amount due automatically

Calculation accuracy:

  • Eliminates manual calculation errors
  • Consistent application of contract terms
  • Automatic retention tracking
  • Accurate payment history

Multi-Contract Support

Wakha supports all major South African contract forms:

  • JBCC — Full JBCC PBA 2018 support
  • NEC — NEC4 payment assessment support
  • GCC — GCC 2015 payment certificate support
  • Custom contracts — Configurable for custom contract terms

Contract-specific features:

  • Contract-specific certificate formats
  • Contract-specific retention rules
  • Contract-specific payment periods
  • Contract-specific variation processes

Digital Signing

Wakha enables digital certificate signing:

  • Electronic signatures — Principal agent signs certificates digitally
  • Audit trail — System logs who signed and when
  • Legal validity — Digital signatures legally valid in South Africa
  • PDF export — Export signed certificates as PDFs

Signing workflow:

  • Certificate generated automatically
  • Sent to principal agent for review
  • Principal agent signs digitally
  • Certificate distributed automatically
  • All parties receive copies instantly

Audit Trail

Wakha maintains complete audit trails:

  • Claim history — All payment claims recorded
  • Assessment history — All assessments logged
  • Certificate history — All certificates tracked
  • Payment history — All payments recorded
  • Change history — All changes logged with timestamps

Audit trail benefits:

  • Complete payment history
  • Dispute resolution support
  • Legal compliance
  • Financial audit support

Payment Tracking

Wakha tracks payments throughout the project:

  • Certificate tracking — Track certificate status (issued, sent, paid)
  • Payment due dates — Automatic calculation of payment due dates
  • Payment receipt — Record when payments are received
  • Overdue alerts — Alerts when payments are overdue
  • Payment forecasting — Forecast future payments based on schedule

Payment management:

  • Real-time payment status
  • Overdue payment alerts
  • Payment history reports
  • Cash flow forecasting

Integration with Project Management

Wakha’s payment certificates integrate with project management:

  • Work completion — Work completion automatically feeds payment certificates
  • Site diary — Site diary entries support payment claims
  • Variations — Variation management integrated with payment certificates
  • Budget tracking — Payment certificates included in budget tracking
  • Cash flow — Payment schedule feeds cash flow forecasting

Integrated workflows:

  • Complete project financial picture
  • Consistent data across modules
  • Reduced duplicate data entry
  • Real-time financial visibility

Builder Plan Features (R2,499/month)

Wakha’s Builder plan includes:

  • JBCC/NEC/GCC payment certificate generation
  • Automatic calculation of amounts
  • Retention tracking and calculations
  • Payment tracking and monitoring
  • Digital certificate distribution
  • Basic reporting

Developer Plan Features (R6,999/month)

Wakha’s Developer plan adds:

  • Advanced variation management
  • Multi-contract support with custom configurations
  • Digital signing workflows
  • Advanced payment forecasting
  • Client portal with payment status
  • API access for integrations
  • Advanced reporting and analytics

Learn more about Wakha’s payment certificate features or request a demo to see how automated payment certificates can improve your cash flow.

Frequently Asked Questions

What’s the difference between JBCC, NEC, and GCC payment certificates?

The main differences are:

JBCC:

  • Monthly certificates issued by principal agent
  • 14-day payment period
  • Standard retention release (50% at practical completion, 50% at final completion)
  • Clear variation order process

NEC:

  • Monthly assessments by project manager
  • 3-week payment period
  • More flexible assessment process
  • Compensation events (variations) handled differently

GCC:

  • Monthly certificates issued by principal agent
  • Payment period varies (typically 14-30 days)
  • Retention terms vary by contract
  • More flexible than JBCC

The certificate format and calculation methods are similar, but timing, terminology, and some processes differ. Choose software that supports your contract form.

Can I claim for materials on site that haven’t been incorporated into work?

It depends on your contract. JBCC contracts may allow payment for specific materials on site (e.g., structural steel, precast concrete) if the contract provides for this. NEC and GCC contracts typically don’t allow payment for materials on site. Check your contract terms — if materials on site aren’t included, you’ll only be paid when materials are incorporated into work.

What happens if the principal agent doesn’t issue a certificate on time?

If the principal agent fails to issue a certificate within the contract deadline, this constitutes a breach of contract. You may be entitled to:

  • Interest on overdue amounts (if contract provides)
  • Potential suspension of work (if contract allows)
  • Dispute resolution procedures
  • Damages for breach of contract

However, try to resolve the issue through communication first before escalating to formal dispute procedures. Late certificates are often due to resource constraints or administrative issues that can be resolved.

How do I dispute a payment certificate if I think work has been under-valued?

If you believe a payment certificate under-values work, you can dispute it:

  1. Review the certificate — Identify specific items you dispute
  2. Gather evidence — Measurement sheets, photos, site diary entries
  3. Notify principal agent — Write formal notice of dispute
  4. Request meeting — Meet to discuss and resolve dispute
  5. Formal procedures — If unresolved, use contract dispute procedures (adjudication, arbitration)

Dispute procedures are typically specified in your contract. Act promptly — most contracts have time limits for disputes.

Can payment certificates be issued for defective work?

Payment certificates should only include work that meets contract quality standards. If work is defective:

  • Principal agent should exclude defective work from certificate
  • Principal agent may deduct amounts for defects (if contract allows)
  • Principal agent may require rectification before certifying payment

However, principal agents must be fair — minor defects that don’t affect functionality may not justify exclusion from payment. The contract typically specifies defect handling procedures.

How does retention work if practical completion is delayed?

If practical completion is delayed, retention release is also delayed. The penultimate certificate (releasing 50% retention) is issued only when practical completion is achieved, regardless of the original programme date. This means:

  • Retention continues accumulating until practical completion
  • 50% retention release delayed until practical completion
  • Final 50% release delayed until final completion

Plan for this in your cash flow forecasts — delayed practical completion means delayed retention release.

What’s included in the final payment certificate?

The final payment certificate includes:

  • All work completed to final completion
  • All final account adjustments
  • All variations settled
  • Remaining retention released (typically final 50%)
  • All outstanding amounts
  • Final settlement of contract

The final certificate closes out the financial aspects of the contract. Ensure all variations, claims, and adjustments are included before agreeing to the final certificate.

Conclusion

Progress payment certificates are essential for construction cash flow. Understanding how they work under JBCC, NEC, and GCC contracts — from contractor claims through assessment, certification, and payment — helps you manage the process effectively and avoid costly disputes.

The payment certificate process is complex, with strict timelines, detailed calculations, and multiple parties involved. Manual management is time-consuming, error-prone, and stressful. Digital payment certificate software like Wakha automates certificate generation, calculations, retention tracking, and payment monitoring, ensuring accuracy, compliance, and timely payments.

If you’re managing construction projects and want to streamline your payment certificate process, Wakha can help. With support for JBCC, NEC, and GCC contracts, automatic calculations, digital signing, and payment tracking, Wakha transforms payment certificate management from a burden into a competitive advantage.

Request a demo to see how automated payment certificates can improve your cash flow and reduce administrative burden.


Related Articles:


Ibhalwe ngu

Wakha Team

Zama i-Wakha mahhala