JBCC Payment Certificates: How to Issue & Manage Progress Payments
Cash flow is the lifeblood of any construction project. In South Africa, where delayed payments are a persistent industry challenge, properly issued payment certificates under the JBCC (Joint Building Contracts Committee) contract forms are critical for maintaining healthy cash flow and avoiding disputes.
According to industry data, payment delays cost South African contractors billions annually in lost productivity, strained relationships, and even business failures. The JBCC payment certificate system exists to provide a structured, legally compliant framework for progress payments — but only if you understand how to issue and manage them correctly.
This comprehensive guide explains everything you need to know about JBCC payment certificates: what they are, how to issue them step-by-step, how retentions work, how variations affect payments, and how construction management software can automate the entire process.
Why Payment Certificates Are Critical for Construction Cash Flow
Construction projects operate on tight margins. Unlike manufacturing businesses that invoice upon delivery, contractors must fund materials, labour, and overhead costs upfront, then wait for payment based on work completed. This creates a cash flow gap that can cripple even well-run construction companies.
Payment certificates under JBCC contracts serve several critical functions:
- Structured payment schedule — Regular interim payments based on work completed, not arbitrary milestones
- Legal protection — Certificates create enforceable payment obligations under the contract
- Dispute prevention — Clear valuation process reduces disagreements about what’s been completed
- Cash flow predictability — Contractors can forecast payments and plan accordingly
- Retention management — Structured system for holding and releasing retention funds
Without properly issued payment certificates, contractors face delayed payments, disputes, and cash flow crises. Understanding the JBCC payment certificate process isn’t optional — it’s essential for operating successfully in the South African construction industry.
What Is a JBCC Payment Certificate?
A JBCC payment certificate is a formal document issued by the principal agent (typically the architect or quantity surveyor) that certifies the value of work completed by the contractor and authorises payment by the employer. Under JBCC PBA 2018 (Principal Building Agreement), payment certificates are the mechanism through which progress payments are made.
The certificate serves as both a valuation document and a payment instruction. It states:
- The gross value of work completed to date
- Any variations or adjustments
- Deductions for retention
- Deductions for previous payments
- The net amount due to the contractor
Payment certificates are legally binding documents. Once issued, they create an obligation on the employer to pay the certified amount within the timeframe specified in the contract (typically 14 days under JBCC PBA 2018 clause 6.2).
The Role of the Principal Agent
The principal agent is responsible for assessing work completed, valuing variations, and issuing payment certificates. This role requires:
- Regular site inspections to verify work completion
- Accurate measurement and valuation of completed work
- Understanding of contract terms, including retention and variation procedures
- Timely certificate issuance within contract deadlines
- Fair and impartial assessment of work quality and completion
The principal agent acts as an independent assessor, balancing the interests of both employer and contractor while ensuring compliance with the contract terms.
Types of Payment Certificates Under JBCC
The JBCC PBA 2018 contract form recognises three types of payment certificates, each serving a different purpose in the payment cycle:
Interim Payment Certificates
Interim payment certificates are issued monthly (or at other intervals specified in the contract) throughout the construction period. They cover work completed since the last certificate and form the basis for regular progress payments.
Key characteristics:
- Issued monthly or at contract-specified intervals
- Cover work completed during the period
- Include variations approved during the period
- Deduct retention (typically 5-10% of gross value)
- Deduct all previous payments
- Create payment obligation for the net amount
Interim certificates keep cash flowing throughout the project, allowing contractors to fund ongoing work without waiting until project completion.
Penultimate Payment Certificate
The penultimate certificate is issued when the principal agent determines that practical completion has been achieved. This certificate is significant because it typically releases half of the retention held throughout the project.
Key characteristics:
- Issued at practical completion
- Releases 50% of retention (subject to contract terms)
- Includes all work completed to practical completion
- May include final variations and adjustments
- Remaining 50% retention continues to be held until final completion
The penultimate certificate provides contractors with a significant cash injection at practical completion, helping fund final accounts preparation and defect rectification work.
Final Payment Certificate
The final payment certificate is issued after all defects have been rectified, final accounts have been agreed, and the principal agent determines that final completion has been achieved. This certificate releases the remaining retention and settles all outstanding amounts.
Key characteristics:
- Issued at final completion
- Releases remaining retention (typically the final 50%)
- Includes all final account adjustments
- Settles all outstanding variations and claims
- Represents final payment under the contract
The final certificate closes out the financial aspects of the contract, releasing all retention and settling all accounts.
Step-by-Step: How to Issue an Interim Payment Certificate
Issuing a JBCC payment certificate requires careful attention to detail and strict adherence to contract procedures. Here’s the step-by-step process:
Step 1: Contractor Submits Payment Claim
The process begins when the contractor submits a payment claim (also called a payment application or valuation). Under JBCC PBA 2018 clause 6.2, the contractor must submit the claim by a specified date each month (typically the 25th or last working day).
The payment claim should include:
- Statement of work completed during the period
- Measurement sheets or supporting documentation
- Details of any variations claimed
- Materials on site (if applicable under the contract)
- Any other amounts claimed (preliminaries, adjustments, etc.)
The contractor’s claim forms the basis for the principal agent’s assessment, but the principal agent is not bound by the contractor’s valuation — they must independently assess the work.
Step 2: Principal Agent Assesses Work Done
The principal agent must visit the site and assess the work completed. This assessment involves:
Site inspection:
- Verifying that claimed work has actually been completed
- Checking work quality and compliance with specifications
- Measuring quantities of work completed
- Identifying any defects or incomplete work
- Noting any work that doesn’t meet contract requirements
Valuation process:
- Measuring quantities against the bill of quantities or schedule of rates
- Applying contract rates to measured quantities
- Valuing preliminaries (site establishment, overheads, etc.) proportionally
- Assessing work quality and applying any deductions for defects
The principal agent must be thorough and fair. Under-valuation can cause cash flow problems for contractors, while over-valuation can expose the employer to paying for incomplete or defective work.
Step 3: Valuation of Variations and Adjustments
Variations are changes to the original contract scope, price, or conditions. Under JBCC PBA 2018, variations must be properly authorised through variation orders before work is executed.
Variation valuation methods:
- Bill rates — Using rates from the original bill of quantities where applicable
- Fair rates — Negotiated rates for work not covered by bill rates
- Cost plus — Actual cost plus overhead and profit percentage (for complex variations)
- Provisional sums — Where variations relate to provisional sum items
Common adjustments included:
- Authorised variation orders executed during the period
- Fluctuations (if applicable under the contract)
- Adjustments for materials on site
- Adjustments for advance payments
- Any other contractually required adjustments
Variations can significantly impact payment certificates. Poor variation management leads to disputes, delayed certificates, and cash flow problems.
Step 4: Deduction of Retention
Retention is a percentage of the gross payment amount held back by the employer as security for defects and incomplete work. Under JBCC PBA 2018, retention is typically 5-10% of the gross value, though this can vary by contract.
Retention calculation:
- Applied to gross value of work completed (including variations)
- Calculated as a percentage of gross value
- Accumulates throughout the project
- First 50% released at practical completion (penultimate certificate)
- Remaining 50% released at final completion (final certificate)
Example retention calculation:
- Gross value this period: R500,000
- Retention rate: 10%
- Retention deducted: R50,000
- Net value before previous payments: R450,000
Retention provides security for the employer but ties up contractor cash flow. Proper retention management is essential for both parties.
Step 5: Deduction of Previous Payments
The principal agent must deduct all previous payments made to the contractor. This includes:
- All previous interim payment certificates
- Any advance payments
- Any direct payments made by the employer
- Any other payments made under the contract
Payment tracking:
- Maintain accurate records of all payments
- Ensure no double-counting of payments
- Account for any payment adjustments or corrections
- Verify payment records match bank statements
Accurate payment tracking prevents over-payment and ensures the certificate reflects the true amount due.
Step 6: Certificate Issued Within Prescribed Timeframe
Under JBCC PBA 2018 clause 6.2, the principal agent must issue the payment certificate within a specified timeframe (typically 7-14 days after receiving the contractor’s claim). This deadline is critical — late certificates delay payments and can breach contract terms.
Certificate contents:
- Certificate number and date
- Project name and contract number
- Period covered by the certificate
- Gross value of work completed
- Value of variations included
- Total gross value
- Retention deducted
- Previous payments deducted
- Net amount due
- Payment due date (typically 14 days from certificate date)
Certificate format:
- Clear, professional presentation
- All calculations shown
- Supporting schedules attached (if required)
- Signed by the principal agent
- Copies to contractor, employer, and quantity surveyor (if applicable)
Once issued, the certificate creates a payment obligation. The employer must pay the certified amount by the due date, or risk breaching the contract.
Retention Explained: Release at Practical Completion and Final Completion
Retention is one of the most misunderstood aspects of construction contracts. Understanding how retention works is essential for managing cash flow and planning project finances.
What Is Retention?
Retention is a percentage of each payment held back by the employer as security. It serves two purposes:
- Security for defects — Ensures contractor rectifies defects during the defects liability period
- Security for incomplete work — Protects employer if contractor fails to complete work
Retention Rates
Retention rates vary by contract but are typically:
- 5% — Common for smaller projects or trusted contractors
- 10% — Standard rate for most projects
- Higher rates — Sometimes applied to high-risk projects or new contractors
The retention rate is specified in the contract and applies to the gross value of work (including variations).
Retention Release Schedule
Under JBCC PBA 2018, retention is released in two stages:
Stage 1: Practical Completion (Penultimate Certificate)
- 50% of total retention is released
- Remaining 50% continues to be held
- Released amount helps contractor fund final accounts and defect rectification
Stage 2: Final Completion (Final Certificate)
- Remaining 50% of retention is released
- All retention is cleared
- Final payment settles all accounts
Retention Calculation Example
Consider a project where:
- Total contract value: R10,000,000
- Retention rate: 10%
- Total retention to be held: R1,000,000
At practical completion:
- Total retention accumulated: R1,000,000
- Released: R500,000 (50%)
- Remaining retention: R500,000
At final completion:
- Remaining retention: R500,000
- Released: R500,000 (final 50%)
- Total retention cleared: R1,000,000
Retention and Cash Flow
Retention significantly impacts contractor cash flow:
- R10M project with 10% retention — R1M tied up until final completion
- Impact — Reduces available cash by retention amount throughout project
- Planning — Contractors must account for retention in cash flow forecasts
Proper retention management requires:
- Accurate tracking of retention accumulated
- Planning for retention release dates
- Understanding contract terms for retention release
- Accounting for retention in project budgets
Variation Orders and How They Affect Payment Certificates
Variations are changes to the original contract scope, and they’re one of the most common sources of payment disputes. Understanding how variations work under JBCC contracts is essential for accurate payment certificates.
What Are Variations?
Variations include:
- Additions — Additional work not in original scope
- Omissions — Work removed from original scope
- Substitutions — Different materials or methods than specified
- Changes — Modifications to design, specification, or programme
Variation Order Process
Under JBCC PBA 2018, variations must follow a formal process:
Step 1: Variation instruction
- Principal agent issues variation instruction
- Contractor acknowledges receipt
- Variation is authorised before work begins
Step 2: Variation execution
- Contractor executes variation work
- Work must comply with contract standards
- Principal agent inspects variation work
Step 3: Variation valuation
- Principal agent values variation
- Uses bill rates, fair rates, or cost plus method
- Variation value added to payment certificate
How Variations Affect Payment Certificates
Variations impact payment certificates in several ways:
Gross value increase:
- Variation value added to gross work value
- Increases total gross value for the period
- Increases retention amount (retention applies to gross including variations)
Timing considerations:
- Variations executed during period included in interim certificate
- Variations authorised but not executed excluded until work done
- Final account variations settled in final certificate
Valuation methods:
- Bill rates — Quick, uses existing rates, preferred method
- Fair rates — Negotiated rates, requires agreement
- Cost plus — Actual cost plus percentage, used for complex variations
Common Variation Disputes
Variation disputes often arise from:
- Unauthorised work — Work done without variation order
- Valuation disagreements — Disputes over variation rates
- Scope disputes — Disagreement about what constitutes variation
- Timing issues — Variations claimed late or not properly documented
Preventing disputes:
- Always obtain variation order before executing work
- Document variation work thoroughly (photos, measurements, records)
- Agree rates before executing work where possible
- Include variations in payment claims promptly
- Maintain clear variation register
Common Disputes and How to Avoid Them
Payment certificate disputes are costly, time-consuming, and damage relationships. Understanding common dispute causes helps prevent them.
Dispute 1: Late Payment Certificates
Problem: Principal agent issues certificates after contract deadline, delaying payments.
Impact:
- Contractor cash flow problems
- Breach of contract by principal agent
- Potential interest claims
- Strained relationships
Prevention:
- Clear contract deadlines for certificate issuance
- Principal agent planning and resource allocation
- Early contractor claim submission
- Automated reminders and workflows
Dispute 2: Under-Valuation of Work
Problem: Principal agent values work below contractor’s assessment, reducing payment.
Impact:
- Reduced cash flow for contractor
- Disputes over measurement and rates
- Potential adjudication or arbitration
- Project delays if contractor disputes
Prevention:
- Clear measurement standards and methods
- Regular site meetings to discuss valuations
- Detailed supporting documentation from contractor
- Fair and transparent valuation process
Dispute 3: Variation Valuation Disputes
Problem: Disagreement over variation rates or whether work constitutes variation.
Impact:
- Delayed variation payments
- Cash flow impact
- Potential contract disputes
- Project delays
Prevention:
- Variation orders issued before work
- Rates agreed before work execution
- Clear variation documentation
- Regular variation register updates
Dispute 4: Retention Release Disputes
Problem: Disagreement about when retention should be released or amounts to be released.
Impact:
- Contractor cash flow tied up
- Disputes over practical completion
- Disputes over defect rectification
- Final account delays
Prevention:
- Clear contract terms for retention release
- Proper practical completion certification
- Timely defect rectification
- Clear final completion procedures
Dispute 5: Defect Deductions
Problem: Principal agent deducts amounts for defects contractor disputes.
Impact:
- Reduced payment amounts
- Disputes over defect responsibility
- Cash flow impact
- Relationship damage
Prevention:
- Clear defect identification and notification
- Fair defect assessment process
- Opportunity for contractor to rectify
- Proper defect documentation
Timeline Requirements: When Claims Must Be Submitted and Certificates Issued
JBCC contracts specify strict timelines for payment claims and certificate issuance. Missing these deadlines can delay payments and breach contract terms.
Contractor Payment Claim Deadlines
Under JBCC PBA 2018 clause 6.2, contractors must submit payment claims by a specified date each month (typically the 25th or last working day of the month).
Claim submission requirements:
- Submitted by contract deadline
- Include all required information
- Supported by measurement sheets and documentation
- Include variation claims
- Submitted to principal agent
Late claim consequences:
- May be excluded from current certificate
- Included in next certificate (delaying payment)
- Potential breach of contract by contractor
Principal Agent Certificate Issuance Deadlines
The principal agent must issue payment certificates within a specified timeframe after receiving the contractor’s claim (typically 7-14 days under JBCC PBA 2018 clause 6.2).
Certificate issuance requirements:
- Issued within contract deadline
- Include all required information
- Accurate calculations
- Properly signed and authorised
- Copies distributed to all parties
Late certificate consequences:
- Breach of contract by principal agent
- Delayed payments to contractor
- Potential interest claims
- Contractual penalties (if specified)
Payment Deadlines
Once a certificate is issued, the employer must pay the certified amount within the payment period specified in the contract (typically 14 days under JBCC PBA 2018 clause 6.2).
Payment requirements:
- Paid by due date specified in certificate
- Paid in full (unless valid set-off)
- Paid to contractor’s nominated account
- Payment confirmation provided
Late payment consequences:
- Breach of contract by employer
- Interest on overdue amounts (if contract provides)
- Potential suspension of work by contractor
- Damage to relationship
Timeline Planning
Effective payment certificate management requires timeline planning:
Monthly cycle example:
- Day 1-24: Work execution and documentation
- Day 25: Contractor submits payment claim
- Day 26-32: Principal agent assesses and issues certificate
- Day 33-46: Employer processes and pays
- Day 47: Payment received by contractor
Critical path:
- Contractor claim submission deadline
- Principal agent certificate deadline
- Employer payment deadline
- Each deadline affects the next
Missing any deadline delays the entire payment cycle, impacting cash flow and potentially breaching contract terms.
How Wakha Automates the Entire Payment Certificate Process
Managing JBCC payment certificates manually — tracking claims, calculating retentions, valuing variations, issuing certificates, and monitoring payments — is time-consuming, error-prone, and stressful. Construction management software like Wakha automates these workflows, ensuring accuracy, compliance, and timely payments.
Automatic Payment Certificate Generation
Wakha generates JBCC payment certificates automatically based on:
- Work completed and measured
- Variations authorised and executed
- Retention rates and calculations
- Previous payments made
- Contract terms and rates
Certificate features:
- Professional certificate format
- All calculations shown
- JBCC-compliant structure
- Digital signatures
- PDF export for distribution
Retention Tracking and Calculations
Wakha automatically tracks retention throughout the project:
- Calculates retention on each payment
- Tracks total retention accumulated
- Identifies retention release dates
- Calculates retention releases at practical and final completion
- Generates retention reports
Retention management:
- Automatic retention calculations
- Retention release tracking
- Retention reports for cash flow planning
- Alerts for retention release dates
Variation Management
Wakha manages variations from instruction to payment:
- Variation order creation and tracking
- Variation work execution tracking
- Variation valuation (bill rates, fair rates, cost plus)
- Variation inclusion in payment certificates
- Variation register and reporting
Variation features:
- Digital variation orders
- Variation approval workflows
- Automatic variation valuation where possible
- Variation tracking and reporting
- Variation impact on cash flow
Payment Tracking and Monitoring
Wakha tracks all payments throughout the project:
- Payment certificate tracking
- Payment due dates and deadlines
- Payment receipt confirmation
- Overdue payment alerts
- Payment history and reporting
Payment management:
- Automatic payment due date calculation
- Payment receipt tracking
- Overdue payment alerts
- Payment history reports
- Cash flow forecasting based on payment schedule
Integration with Project Management
Wakha’s payment certificate module integrates with project management:
- Work completion linked to payment certificates
- Site diary entries support payment claims
- Budget tracking includes payment certificates
- Cash flow forecasting based on payment schedule
- Client portal shows payment status
Integrated workflows:
- Work completion automatically feeds payment certificates
- Site diary supports payment claim documentation
- Budget tracking includes certified amounts
- Cash flow forecasts based on payment schedule
- Real-time payment status visibility
Real-World Benefits
Using Wakha for payment certificate management delivers tangible benefits:
Time savings:
- Automatic calculations eliminate manual work
- Certificate generation in minutes, not hours
- Reduced administrative burden
- More time for site management and business development
Accuracy:
- Automatic calculations reduce errors
- Consistent application of contract terms
- Accurate retention and variation tracking
- Reliable payment records
Compliance:
- JBCC-compliant certificate format
- Automatic deadline tracking
- Contract term compliance
- Audit trail for all payments
Cash flow:
- Faster certificate generation
- Better payment tracking
- Improved cash flow forecasting
- Reduced payment delays
Getting Started with Wakha
Wakha’s payment certificate module is available on all plans:
- Builder plan (R2,499/month) — Basic payment certificate generation
- Developer plan (R6,999/month) — Full payment certificate automation with variation management
- Enterprise — Custom payment certificate workflows and integrations
The module includes:
- JBCC/NEC/GCC payment certificate generation
- Automatic retention calculations
- Variation management and valuation
- Payment tracking and monitoring
- Cash flow forecasting
- Digital certificate distribution
To see how Wakha can streamline your payment certificate process, request a demo or explore Wakha’s features.
Frequently Asked Questions
What happens if the principal agent doesn’t issue a payment certificate on time?
If the principal agent fails to issue a payment certificate within the contract deadline, this constitutes a breach of contract. The contractor may be entitled to:
- Interest on overdue amounts (if contract provides)
- Potential suspension of work (if contract allows)
- Dispute resolution procedures
- Damages for breach of contract
However, contractors should first attempt to resolve the issue through communication before escalating to formal dispute procedures.
Can a contractor dispute a payment certificate?
Yes. Contractors can dispute payment certificates if they believe:
- Work has been under-valued
- Variations have been incorrectly valued or excluded
- Retention has been incorrectly calculated
- Defect deductions are unfair or incorrect
- Other amounts have been incorrectly calculated
Dispute procedures are typically specified in the contract and may include:
- Written notice of dispute
- Meeting to resolve dispute
- Adjudication (if contract provides)
- Arbitration or litigation (if dispute not resolved)
How is retention released if practical completion is delayed?
If practical completion is delayed, retention release is also delayed. The penultimate certificate (releasing 50% retention) is issued only when practical completion is achieved, regardless of the original programme date. Contractors should plan for this in their cash flow forecasts.
What happens to variations that aren’t included in interim certificates?
Variations that are authorised but not yet executed are excluded from interim certificates until the work is completed. Variations executed but not yet valued may be included at a provisional value, with final valuation in the final account. All variations should be settled in the final certificate.
Can payment certificates be issued for work that doesn’t meet quality standards?
Payment certificates should only include work that meets contract quality standards. If work is defective or incomplete, the principal agent should:
- Exclude defective work from the certificate
- Deduct amounts for defects (if contract allows)
- Require rectification before certifying payment
However, the principal agent must be fair and reasonable — minor defects that don’t affect functionality may not justify exclusion from payment.
Conclusion
JBCC payment certificates are the foundation of construction project cash flow. Understanding how to issue and manage them correctly — from contractor claims to principal agent assessment, retention calculations, variation management, and final accounts — is essential for operating successfully in the South African construction industry.
The process is complex, with strict timelines, detailed calculations, and multiple parties involved. Manual management is time-consuming, error-prone, and stressful. Construction management software like Wakha automates payment certificate generation, retention tracking, variation management, and payment monitoring, ensuring accuracy, compliance, and timely payments.
If you’re managing construction projects under JBCC contracts and want to streamline your payment certificate process, Wakha can help. Request a demo to see how automated payment certificate generation can improve your cash flow and reduce administrative burden.
Related Articles:
- JBCC vs NEC vs GCC: Which Construction Contract Should You Use?
- Construction Cash Flow Management in South Africa: Complete Guide
- Progress Payment Certificates in South Africa: What Contractors Need to Know
- Delayed Payments in Construction: How to Protect Your Cash Flow
- Best Construction Management Software South Africa 2026
Written by
Wakha Team